Planning an ADU: From Feasibility to Move-In

An accessory dwelling unit can house a parent, an adult child or a tenant, and Washington's ADU law means most residential lots in Seattle and the Eastside can have up to two. Getting from idea to move-in usually takes twelve to eighteen months for a backyard cottage and eight to twelve for a conversion. The projects that go smoothly are the ones that check the lot carefully before spending on design.

A small glass-walled studio on a wooden platform in tall grassGlass studio
An open-plan small house with a timber stair, kitchen and seatingOpen plan
A white house seen over a tall wooden fence and treesBehind the fence

Step 1: Decide what the unit is for

  • Family member: accessibility, proximity to the main house, privacy for both households.
  • Rental income: a layout that rents well, separate utilities or sub-meters, durable finishes, parking or transit access.
  • Flexibility: a home office now, a rental later, family use after that.

The purpose drives size, layout and finish level.

Step 2: Choose a type

TypeTypical all-in costProsCons
Detached cottage$300,000 – $500,000Most privacy, most rentableHighest cost, utilities and site work
Garage conversion$120,000 – $220,000Lowest cost if the garage is soundLoses parking and storage
Attached or basement unit$150,000 – $300,000Shares structureNeeds headroom, egress and fire separation

Step 3: Check the lot

This is the step people skip and regret.

  1. Zoning and ADU rules. Your city's code sets size, height, setbacks and placement within state law.
  2. Critical areas. Wetlands, streams, steep slopes and their buffers can remove buildable area.
  3. Lot coverage and impervious limits. On smaller lots, the house and driveway may use most of the allowance.
  4. Trees. Significant or protected trees can decide where a cottage fits.
  5. Utilities. Where sewer, water and power connect, and how far and how deep the trench to a backyard unit must go.
  6. Access. Alley access, side yard width and how construction equipment reaches the back.
  7. Covenants. HOA covenants are private agreements; if yours seem to restrict ADUs, get legal advice.

A feasibility review by a designer or builder, often for a modest fee, answers these before design.

Step 4: Budget beyond the building

The building itself is the visible cost. These lines surprise people:

  • Utility trenching and connections: often $25,000 to $60,000 for a detached unit.
  • Side-sewer work where the existing line is old or undersized.
  • Impact and connection fees, which state law caps for ADUs but does not eliminate.
  • Site work: grading, drainage, paths, fencing, landscaping repair.
  • Appliances and furnishings for a rental.

Small units do not save as much as people expect, because a kitchen, a bathroom, a foundation and a roof cost nearly the same at 600 square feet as at 900.

Step 5: Design

Some cities offer pre-approved ADU plans that shorten review when they fit the lot. Custom designs take longer but fit the site and the purpose. Design choices that pay off: a separate entrance with privacy from the main house, plenty of light, storage, in-unit laundry, and a layout that works for the intended occupant.

Step 6: Permits

An ADU needs a building permit with architectural and structural drawings, an energy code worksheet and utility plans, plus electrical, plumbing and mechanical permits, and often tree, stormwater and side-sewer reviews. Review times run from several weeks to several months.

Step 7: Construction

A detached unit takes four to seven months on site: site work and utilities, foundation, framing, roof, rough-ins, insulation, drywall, finishes. Conversions take two to four months. Expect the utility work to be the most disruptive part for the main house.

Step 8: Move-in or rent

A certificate of occupancy ends the permit. If renting, check whether your city requires rental registration or inspection, set up a lease that meets Washington landlord-tenant law, and confirm insurance for the rental use.

Common mistakes

  • Paying for design before checking buffers, trees and utilities.
  • Building too small to rent well.
  • Underestimating utilities and site work.
  • Assuming a pre-approved plan fits without adjustment.
  • Ignoring covenants until late in the process.